On- Farm Water and Soil Management Project
[OWSOM]
|
Main Place
|
Soil, Water and Environment Research Institute (SWERI) |
Dates
|
Starting Date: 1/1987 Ending Date: 0/0 |
Objectives
|
- The goal of the project is to provide Egypt with a replicable and adaptable system for On–Farm soil and water management practices that are environmentally sustainable, economically sound socially acceptable
|
Achievements
|
- Lining 412.37 Km of earth mar was in eleven governorates, 205.4 Km were lined with farmers participation, 196.18 Km were lined by farmers self efforts and 10.8 Km were lined in governorates farms, durms, during the period from 1998 to 2005 In this year 2006, 37 Km will be lined at for teen govemorates ( Kafr El – Sheikh, El – Behira, El Kharbia, El Sharkia El- Monofia, El- Dakahlia, Dameta, El- Fayom, El- Menia, Baneswief, Assuit, Sohag, Qena and El- Calubia)
|
Participated Researchers
|
|
Cooperating and Funds
|
Co-Operation Internal Establishment
|
|
|
|